.10 a pound glass fee in 2027. Comments close 4 p.m. on 30 October 2026." /> .10 a pound glass fee in 2027, and comments close at 4 p.m. on 30 October." /> .10 a pound glass fee in 2027. Comments close 4 p.m. on 30 October 2026." /> .10 a pound glass fee in 2027, and comments close at 4 p.m. on 30 October." /> Oregon RMA rulemaking 3: glass, exemptions, comments 30 Oct .10 a pound glass fee in 2027. Comments close 4 p.m. on 30 October 2026." />
Skip to content
Specialized Packaging Market Intelligence and Strategic AdvisoryPackaging Intelligence. Clearer Decisions. Stronger Growth.

SPI NewsUnited States · Packaging EPR

Oregon's rulemaking 3 would cut PRO glass duties and could trim the $0.10 a pound fee. Comments close 30 October

Oregon DEQ holds its second hearing on Recycling Modernization Act rulemaking 3 at 6 p.m. on 21 October; the package could partly cut a $0.10 a pound glass fee in 2027, and comments close at 4 p.m. on 30 October.

By the SPI teamPublished 15 min read

CAA's plan puts local government expansion funding at $59.1 million in 2027, about three times the 2026 figure, which is the cost wave DEQ wants to spread Unit: USD million
CAA's plan puts local government expansion funding at $59.1 million in 2027, about three times the 2026 figure, which is the cost wave DEQ wants to spread3 bars. Largest: 2027, 59.08.20272027: 59.08 USD million59.0820262026: 19.10 USD million19.1020252025: 3.34 USD million3.34CAA's plan puts local government expansion funding at $59.1 million in 2027, about three times the 2026 figure, which is the cost wave DEQ wants to spread3 bars. Largest: 2027, 59.08.20272027: 59.08 USD million59.0820262026: 19.10 USD million19.1020252025: 3.34 USD million3.34

Source: CAA Oregon, Oregon Program Plan (2025 to 2027), Table 1, submission of 1 Sep 2026, consulted, checked 31 Oct 2026.

Local government system expansion disbursements, not producer fees. Total of $81,525,504 is stated by CAA. Rounded to two decimals by SPI.

Show the data
CAA's plan puts local government expansion funding at $59.1 million in 2027, about three times the 2026 figure, which is the cost wave DEQ wants to spread (USD million)
YearExpansion funding (USD million)
202759.08
202619.10
20253.34

Key takeaways

  • DEQ’s notice of 21 September 2026 sets a comment deadline of 4 p.m. on 30 October 2026, with hearings on 20 October at 10 a.m. and 21 October at 6 p.m.
  • The notice says reduced PRO glass duties could bring a partial reduction in 2027 of the $0.10 a pound glass fee paid in 2026, and removes an incentive paid to local governments that collect glass.
  • The notice lists new exemptions for leased reusable plastic containers, gaylords of 33.8 ft3 or more, and raw-meat film until 2032.
  • DEQ says it intends to send the rules to the Environmental Quality Commission on or after 14 January 2027, and the rules take effect only if the commission adopts them.
  • SPI analysis: CAA’s own September 2026 plan submission puts 72% of its 2025 to 2027 local government expansion funding in 2027, by SPI’s calculation, which explains why fee timing sits at the centre of the package.
Comments close at 4 p.m. on 30 October, 2,909 producers are CAA members, and the 2026 glass fee is $0.10 a pound

30 Oct 2026

Comment deadline

4 p.m., Pacific time

DEQ notice

2,909

CAA producer-members registered in 2025

as reported by CAA

DEQ notice

$0.10

Glass packaging fee, 2026

USD per pound; partial cut possible in 2027

DEQ notice

Source: DEQ, Notice of Proposed Rulemaking, checked 31 Oct 2026.

The Oregon Department of Environmental Quality (DEQ) holds the second of two public hearings at 6 p.m. on 21 October 2026 on its third set of Recycling Modernization Act rules, which would shrink producer-funded glass collection and add new exemptions.

The package matters to boards now because it reaches the 2027 invoices. DEQ’s notice of 21 September says reduced glass duties could partly reduce the $0.10 a pound fee that glass packaging producers paid in 2026, and that the wider amendments would spread investment to avoid a spike in producer fees in 2027. The same notice expects about 25 cents a month in costs to shift to residential customers.

The rules also touch firms well beyond glass. Leased reusable plastic containers, large industrial gaylords and raw-meat film would leave the fee base, about 50 composting facilities would face new data costs, and fewer than 10 metal remelters would get a reporting reprieve through 2032. Circular Action Alliance (CAA), the state’s only approved producer responsibility organisation (PRO), reported 2,909 producer-members registered in 2025.

How Oregon's producer-funded recycling system works

Oregon’s Recycling Modernization Act became law in 2021 and took effect on 1 January 2022, according to DEQ’s producer obligations summary cited in SPI’s tracker record PR-US-002. It makes producers of packaging, printing and writing paper and food serviceware fund much of the residential recycling system through a PRO.

DEQ approved CAA’s programme plan for 2025 to 2027 on 21 February 2025, covered producers have had to register with an approved PRO from 2025 onward, and CAA could start charging fees on 1 July 2025, DEQ’s Producers of Covered Products page says. The page states that CAA sets fee rates, that they “will change annually”, and that failing to join a PRO is a Class 1 violation with fines of up to $25,000 a day.

Fees run on supply data. From 31 May 2026, producers owe CAA their prior-year supply data by 31 May each year, and DEQ notes that fee deadlines are internal to CAA6. SPI’s tracker record notes that the 2025 data filed this year set 2027 fees.

Fees are also modulated. DEQ approved CAA’s ecomodulation amendment on 12 September 2025 and, in its approval letter, directed that the Tier 2 and Tier 3 bonus multipliers rise from 2.25 and 2.5 to 2.5 and 3.0. A private recycling exemption lets producers deduct material recycled outside the commingled system, applied to the next year’s invoices.

DEQ writes the operating rules in Oregon Administrative Rules (OAR) division 340-090. Rulemaking 3 is the third round of amendments since the first rules of 2023, which DEQ’s notice says were updated in 2024. It runs from September 2025 to early 2027, with an 11-member advisory committee that met five times between November 2025 and July 2026.

“Proposed rules only become effective if the Environmental Quality Commission adopts them.” Oregon DEQ, Notice of Proposed Rulemaking, 21 September 2026

What has happened since the notice of 21 September

October 2025: exemption requests. DEQ’s exemptions page shows it took requests for new covered product exemptions from 1 to 31 October 2025 and presented a rule concept to the advisory committee on 27 January 20267. Those requests fed the exemptions now proposed.

April 2026: glass loses its special status. CAA’s cover letter of 1 September 2026 says DEQ removed the “Specifically Identified Material” designation for glass and shredded paper on 1 April 2026. DEQ’s glass collection technical workgroup met on 15 and 28 April 2026, the rulemaking page shows. A second workgroup, on what counts as effectively composted, met on 26 January and 17 February 2026.

November 2025 to July 2026: the advisory committee. The 11-member committee met on 13 November 2025 and on 27 January, 30 March, 27 May and 20 July 2026, the rulemaking page shows1. Its fifth meeting took topic papers on convenience standards, transport cost reimbursement, multifamily service and DEQ’s draft fiscal and economic impact statement.

11 September 2026: temporary glass rules. The Environmental Quality Commission listed “Recycling Modernization Act Temporary Rulemaking” as action item G on 11 September 2026, its meeting page shows5. DEQ’s notice says the commission adopted temporary rules in September 2026, identical to the proposed permanent glass rules.

21 September: the notice is published. DEQ’s Notice of Proposed Rulemaking, titled “Recycling Modernization Act Rulemaking 3 (2026)”, is dated 21 September 2026 and opened 39 days of comment to 30 October, by SPI’s calculation. Two sets of draft rules sit beside it on the rulemaking page, one with edits highlighted and one with edits incorporated.

20 and 21 October: hearings. The first hearing ran on 20 October at 10 a.m. and the second starts on 21 October at 6 p.m., both by Zoom or toll-free phone with no pre-registration, the rulemaking page says1. SPI has not yet confirmed who testified at the first hearing.

Next: 30 October and 14 January. DEQ says it will consider only comments received by 4 p.m. on 30 October, sent by email to RMARulemaking3@deq.oregon.gov, by post or as hearing testimony. It intends to submit the rules to the commission on or after 14 January 2027, and its rulemaking page targets adoption in January or February 2027.

“DEQ will only consider comments on the proposed rules that DEQ receives by 4 p.m., on Oct. 30, 2026.” Oregon DEQ, Notice of Proposed Rulemaking, 21 September 2026

Comments close on 30 October, the rules go to the commission no earlier than 14 January, and glass depot rules start on 1 July 2027
  • past
  • event
  • next
Comments close on 30 October, the rules go to the commission no earlier than 14 January, and glass depot rules start on 1 July 202710 dated items from 1 Oct 2025 to 1 Jan 2033.2025202620272028202920302031203220332034Today1 Oct 2025: DEQ opens a month for new exemption requests1 Apr 2026: DEQ removes special designation for glass and shredded paper11 Sep 2026: EQC takes temporary glass rules as action item G21 Sep 2026: Notice of proposed rulemaking dated21 Oct 2026: Second public hearing, 6 p.m.30 Oct 2026: Comments close, 4 p.m.14 Jan 2027: Earliest date DEQ submits rules to the EQC1 Jul 2027: Draft glass depot provisions take effect1 Jan 2028: Updated PRO plans begin, running to 31 Dec 20321 Jan 2033: Remelter reporting reprieve endsComments close on 30 October, the rules go to the commission no earlier than 14 January, and glass depot rules start on 1 July 202710 dated items from 1 Oct 2025 to 1 Jan 2033.20252027202920312033Today1 Oct 2025: DEQ opens a month for new exemption requests1 Apr 2026: DEQ removes special designation for glass and shredded paper11 Sep 2026: EQC takes temporary glass rules as action item G21 Sep 2026: Notice of proposed rulemaking dated21 Oct 2026: Second public hearing, 6 p.m.30 Oct 2026: Comments close, 4 p.m.14 Jan 2027: Earliest date DEQ submits rules to the EQC1 Jul 2027: Draft glass depot provisions take effect1 Jan 2028: Updated PRO plans begin, running to 31 Dec 20321 Jan 2033: Remelter reporting reprieve ends
  1. DEQ opens a month for new exemption requestspast
  2. DEQ removes special designation for glass and shredded paperpast
  3. EQC takes temporary glass rules as action item Gpast
  4. Notice of proposed rulemaking datedpast
  5. Second public hearing, 6 p.m.event
  6. Comments close, 4 p.m.next
  7. Earliest date DEQ submits rules to the EQCnext
  8. Draft glass depot provisions take effectnext
  9. Updated PRO plans begin, running to 31 Dec 2032next
  10. Remelter reporting reprieve endsnext

Source: DEQ rulemaking page and notice, 21 Sep 2026; EQC meeting page; DEQ exemptions page; draft OAR 340-090-0630, 0670 and 0720, checked 14 Oct 2026.

Show the data
Comments close on 30 October, the rules go to the commission no earlier than 14 January, and glass depot rules start on 1 July 2027
DateLabelCategoryLink
2025-10-01DEQ opens a month for new exemption requestspasthttps://www.oregon.gov/deq/recycling/Pages/RMA-Exemptions.aspx
2026-04-01DEQ removes special designation for glass and shredded paperpasthttps://www.oregon.gov/deq/recycling/Documents/CAAORLetter202609.pdf
2026-09-11EQC takes temporary glass rules as action item Gpasthttps://www.oregon.gov/deq/about-us/eqc/Pages/202609.aspx
2026-09-21Notice of proposed rulemaking datedpasthttps://ormswd2.synergydcs.com/ORMSCMSearchDEQ/Search/DocumentStream.ashx?uri=7116831
2026-10-21Second public hearing, 6 p.m.eventhttps://www.oregon.gov/deq/rulemaking/Pages/rma2026.aspx
2026-10-30Comments close, 4 p.m.nexthttps://ormswd2.synergydcs.com/ORMSCMSearchDEQ/Search/DocumentStream.ashx?uri=7116831
2027-01-14Earliest date DEQ submits rules to the EQCnexthttps://ormswd2.synergydcs.com/ORMSCMSearchDEQ/Search/DocumentStream.ashx?uri=7116831
2027-07-01Draft glass depot provisions take effectnexthttps://ormswd2.synergydcs.com/ORMSCMSearchDEQ/Search/DocumentStream.ashx?uri=7116830
2028-01-01Updated PRO plans begin, running to 31 Dec 2032nexthttps://ormswd2.synergydcs.com/ORMSCMSearchDEQ/Search/DocumentStream.ashx?uri=7116830
2033-01-01Remelter reporting reprieve endsnexthttps://ormswd2.synergydcs.com/ORMSCMSearchDEQ/Search/DocumentStream.ashx?uri=7116830

What the proposed rules would change

The notice summarises changes across more than 20 rules in OAR divisions 340-012, 340-090, 340-093, 340-096 and 340-097. The table sets out the items with the clearest cost effect for producers, the PRO and service providers, in DEQ’s words where the notice is specific.

Glass, exemptions and the plan calendar carry the money in rulemaking 3, while most other changes are corrections and clarifications
RuleProposed changeWhat it means
OAR 340-090-0630, 0640 and 0650PRO glass collection duties reduced; incentive to local governments that collect glass removedLower PRO operating cost; a partial cut in the $0.10 a pound glass fee possible in 2027
OAR 340-090-0630(4)(c)Glass bottles and jars to be collected at depots in listed wastesheds from 1 July 2027Some councils may stop on-route glass collection
OAR 340-090-0840 and new 0841Exemptions for leased reusable plastic containers, four industrial formats including gaylords of 33.8 ft3 or more, and raw-meat film until 2032Those formats leave the producer fee base
OAR 340-090-0670(3)(e)Self-attestation and disposition reporting for remelters of loose scrap metal not required until 1 Jan 2033Fewer than 10 facilities avoid about five years of costs
OAR 340-090-0670(3)(d)A PRO reporting step for certain materials starts with quarterly data from 1 Jan 2030Delays a PRO compliance cost
OAR 340-090-0720Updated PRO plans run from 1 Jan 2028 to 31 Dec 2032Sets the next five-year plan window
OAR 340-096 composting rules"Effectively composted" definition updated; DEQ authority to decide qualifying materialsAbout 50 composting facilities face data costs
OAR 340-090-0770 and 0820Transport reimbursement and processor commodity risk fee rules adjustedChanges to payment mechanics
OAR 340-097-0120Commingled recycling processing facilities added to permit and disposal feesNew permit fee line for processors

Source: DEQ, Notice of Proposed Rulemaking, 21 Sep 2026; draft rules, edits incorporated, consulted, checked 31 Oct 2026.

Summary of proposed text. Proposed rules take effect only if the EQC adopts them. Not legal advice; check the text or counsel.

Glass. The notice says the glass amendment would cut the PRO’s obligations and its operating costs, reflected in “a significantly lower per-pound fee paid by the producers of glass packaging, starting in 2027”. It frames this as a possible partial reduction of the 2026 rate of $0.10 a pound in 2027, with further reductions for 2028, and notes that CAA’s board sets fees, not DEQ.

Depots. The incorporated draft of OAR 340-090-0630 keeps glass bottles and jars on the PRO list, but from 1 July 2027 only in the wastesheds identified in subsection (4)(c), where the listed materials “must be collected at depots”3. That date falls six months after the earliest submission date to the commission.

Exemptions. The notice proposes exempting leased reusable plastic containers, four formats of industrial-only specialty packaging including gaylords of 33.8 ft3, the standard size, or larger, and “Film and flexible plastic packaging used in direct contact with raw meat, excluding trays.” The raw-meat exemption is proposed to expire in 2032. SPI has not yet confirmed the exemption wording in the draft rule text itself.

Remelters. Draft OAR 340-090-0670(3)(e) says self-attestation, disposition reporting and a related checking step for facilities that remelt loose scrap metal from Oregon, and take no Oregon-origin baled material, “are not required until January 1, 2033.” In effect, these remelters are exempt from that checking step through 2032.

Plan calendar. Draft OAR 340-090-0720 says the first set of updated plans will run from 1 January 2028 to 31 December 2032. The current CAA plan covers 2025 to 2027, so the next plan is the first five-year one.

Acceptance lists. The notice’s summary of OAR 340-090-0630 lists changes for disinfectant containers, automotive fluids such as diesel exhaust fluid and washer fluid, aerosols and cylinders, paint containers, PET colours, shredded paper, spray caps and scrap metal. The incorporated draft adds pressurised cylinders to the PRO list from 1 January 20303.

Multifamily and payments. For OAR 340-090-0030, the notice says tenants are clarified as customers and compliance with the adequate-space rule for multifamily recycling is delayed by two years. Under OAR 340-090-0770 and 0820, transport reimbursement is aligned with consolidation points and tip fees, and the processor commodity risk fee gets a new reporting schedule, with no funding for stockpiled material.

Producers and life cycle rules. OAR 340-090-0860 changes producer definitions, covering fee obligation trading, “remote sale”, “consumer” and manufacturer wording. The life cycle rules in OAR 340-090-0900 to 0930 add a SKU “batch” concept and core product category rules, which matters to the 25 largest producers whose first evaluations fall due by 31 December 2026, DEQ’s producer page says.

The private recycling exemption shows how much tonnage an exemption route can move. DEQ’s exemptions page lists 2025 pooled volumes used in the 2026 exemption process, led by tertiary corrugated cardboard7.

Tertiary corrugated cardboard made up 215,872 tons of the pooled volumes in Oregon's 2026 private recycling exemption process Unit: tons, 2025 pooled volumes
Tertiary corrugated cardboard made up 215,872 tons of the pooled volumes in Oregon's 2026 private recycling exemption process3 bars. Largest: Tertiary corrugated cardboard, 215,872.Tertiary corrugated cardboardTertiary corrugated cardboard: 215,872 tons, 2025 pooled volumes215,872Shredded paperShredded paper: 12,703 tons, 2025 pooled volumes12,703Non-consumer pallet wrapNon-consumer pallet wrap: 7,876 tons, 2025 pooled volumes7,876Tertiary corrugated cardboard made up 215,872 tons of the pooled volumes in Oregon's 2026 private recycling exemption process3 bars. Largest: Tertiary corrugated cardboard, 215,872.Tertiary corrugated cardboardTertiary corrugated cardboard: 215,872 tons, 2025 pooled volumes215,872Shredded paperShredded paper: 12,703 tons, 2025 pooled volumes12,703Non-consumer pallet wrapNon-consumer pallet wrap: 7,876 tons, 2025 pooled volumes7,876

Source: DEQ, Recycling Modernization Act exemptions page, consulted, checked 31 Oct 2026.

Volumes used with the Passive and Limited-Active pathways. These are an existing exemption route, separate from the new exemptions proposed in rulemaking 3.

Show the data
Tertiary corrugated cardboard made up 215,872 tons of the pooled volumes in Oregon's 2026 private recycling exemption process (tons, 2025 pooled volumes)
MaterialPooled volume (tons, 2025 pooled volumes)
Tertiary corrugated cardboard215,872
Shredded paper12,703
Non-consumer pallet wrap7,876

Industry reaction

“The proposed amendments would avoid a spike in producer fees in 2027 by allowing for an extended timeline of investments into Oregon’s modernized recycling system.”

Oregon DEQ, state regulator, Notice of Proposed Rulemaking, statement of need, 21 September 2026

The notice ties the spike to system expansion costs, including larger capital assets for local governments and service providers and processor sorting equipment needed for 2028 performance standards.

“CAA expects rulemaking changes to go into effect in 2028, after CAA’s 2027 producer supply reporting window.”

Circular Action Alliance Oregon, the state’s PRO, programme plan amendment cover letter to DEQ, 1 September 2026

CAA’s letter adds a commitment to adjust its operating and funding plans if PRO glass rules change, and asks for approval by December 2026 so it can update its producer portal before 2027 reporting opens.

“Oregon DEQ has turned the scheme into an expensive program seeking to manipulate end-markets.”

Glass Packaging Institute, US glass container trade body, article first published in Glass International, February 2026

The Glass Packaging Institute says Colorado’s glass fees are one-third of Oregon’s, and that the approved plan would add 3,000 to 4,000 tons of recovered glass, under 1% of existing levels. CAA’s 2026 schedules show glass at 4.0 cents a pound in Colorado against 10.0 cents in Oregon, about 40% by SPI’s calculation.

The glass industry welcomed the earlier step. In a statement of 22 July 2026 carried by Waste Advantage Magazine, the Institute backed DEQ’s decision to reclassify glass from 1 July 2027 and said other state programmes charge glass producers less than half of Oregon’s rate, as reported by that publisher and not confirmed in an official source16.

Not every advisory committee member accepted the framing. DEQ’s notice records committee concern about “the appearance of certainty” on glass fee reductions, and names a CAA representative among committee members.

CAA has kept fee decisions with its national structure. Its amended plan of 4 May 2026 says decisions on programme budgeting and producer fees continue to sit with the National Board, so the 2027 glass rate will come from that board rather than from Oregon staff or DEQ10. The same plan already cut capital for curbside glass, as the next section sets out.

SPI has not yet confirmed published comments on rulemaking 3 from AMERIPEN, the Association of Oregon Recyclers, the League of Oregon Cities or individual brand owners. Comments filed by 30 October will be part of the record DEQ sends to the commission.

Who gains and who pays from glass to compost

Glass packaging producers. They paid $0.10 a pound in 2026, the notice says, and stand to gain most if CAA’s board passes on the PRO’s lower glass costs from 2027. DEQ’s notice does not put a figure on the 2027 rate. CAA’s 2027 Oregon fee schedule, published on 1 October 2026, sets glass bottles and jars at a $0.04 a pound base rate and a $0.00 final rate after reserve drawdowns.

Local governments that collect glass. They lose the current incentive paid to councils running glass collection. CAA’s plan already says “Requests for new trucks and carts for curbside collection of glass are not being scheduled”, and offers instead an incentive equal to the cost of managing glass at depots9.

Residents. The notice expects about 25 cents a month in costs to shift to residential customers who pay for recycling or garbage service. That is $3 a year for each household account, by SPI’s calculation, and the notice says smaller and more remote communities may stop on-route glass collection.

Reuse and industrial packaging. Leasing businesses for reusable plastic crates and users of gaylords of 33.8 ft3 or more would drop out of the fee base. The notice does not count the firms or tonnage involved.

Meat packers and their film suppliers. Raw-meat film, excluding trays, is exempt until 2032 under the proposal, which removes that film from producer reports until the exemption expires.

Composters. About 50 Oregon composting facilities, likely small businesses under DEQ’s 50-employee test, would carry data-collection costs to support submissions on which packaging is effectively composted.

Remelters. Fewer than 10 Oregon facilities that remelt loose shredder metal avoid about five years of costs, the notice says.

Paper producers. Shredded paper lost its special designation alongside glass on 1 April 2026, CAA’s letter says, and the notice lists shredded paper among the acceptance list changes. Shredded paper also made up 12,703 tons of the pooled private recycling volumes on DEQ’s exemptions page.

Circular Action Alliance and its members. CAA reported 2,909 producer-members registered in 2025. Its plan’s Table 1 shows local government expansion funding of $3,340,476 in 2025, $19,103,118 in 2026 and $59,081,910 in 2027, a total of $81,525,504.

Glass producers and remelters gain, while councils that collect glass and residents absorb costs
GroupExposureFigureSource
Glass packaging producers2026 glass fee, partial cut possible in 2027$0.10 a poundDEQ notice
Residential customersExpected cost shiftAbout 25 cents a monthDEQ notice
Local governments collecting glassIncentive removedNot statedDEQ notice
Composting facilitiesNew data costsAbout 50 facilitiesDEQ notice
Remelters of loose shredder metalReporting reprieve to 1 Jan 2033Fewer than 10 facilitiesDEQ notice; draft OAR 340-090-0670
CAA producer-membersRegistered in 20252,909DEQ notice, citing CAA
Local governments, allCAA expansion funding, 2027$59,081,910CAA plan, Table 1

Source: DEQ, Notice of Proposed Rulemaking, 21 Sep 2026; CAA Oregon plan submission, 1 Sep 2026; draft OAR 340-090-0670, checked 31 Oct 2026.

Figures differ in unit, year and scope. Do not add them up or rank them. USD only.

The fee-timing problem behind the 2027 invoices

The package arrives late in the 2027 fee cycle. Producers filed their 2025 supply data by 31 May 2026, and those data set 2027 fees, yet the commission vote cannot come before 14 January 2027 under DEQ’s notice. CAA’s letter of 1 September says it expects the rule changes to take effect in 2028, after its 2027 supply reporting window.

The temporary rules bridge part of that gap. The commission adopted glass rules on a temporary basis in September 2026, identical to the proposed permanent rules, so the glass change can be planned into 2027 while the permanent text is still out for comment.

The funding curve is the second constraint. CAA’s Table 1 puts $59.1 million of local government expansion funding in 2027, against $19.1 million in 2026. DEQ’s answer is to stretch the investment timeline, and its notice cites larger capital assets and sorting equipment for 2028 performance standards as the cost drivers.

SPI analysis

The glass relief and the investment stretch pull in the same direction for 2027 invoices, but neither is a fee decision. DEQ’s notice says CAA’s board sets fees, and advisory committee members warned against implying certainty on glass, so producers should treat CAA’s published 2027 glass rates, a $0.04 a pound base and a $0.00 final rate after reserve drawdowns, as a one-year position rather than a guide to 2028.

DEQ carries costs of its own. The notice says its programme staff spent about 120 hours in total on the rulemaking tasks in 2025 and 2026, and that some changes bring higher short-term costs for DEQ for about four years.

The third constraint is service. If remote councils drop on-route glass after the incentive ends, collection shifts to depots from 1 July 2027 in the listed wastesheds, and DEQ’s notice expects those communities to be more rural or farther from glass end markets.

How Oregon compares with Washington, Minnesota and Colorado

Oregon is amending live operating rules this autumn, while Washington and Minnesota are setting the cost baselines that later reimbursement will rest on. Washington Ecology’s needs-assessments page says its draft preliminary needs assessment takes comments from 1 to 30 October 2026, the same closing day as Oregon13. SPI covered that process in Washington’s needs assessment comments.

Minnesota’s draft 2026 needs assessment takes comments through 13 November, and the PRO must cover at least 90% of costs by 2031, MPCA’s programme page says14. SPI set out the detail in Minnesota’s EPR needs assessment.

Colorado is furthest along on cost. CDPHE’s programme page says the executive director approved CAA’s plan in December 2025, that CAA “will reimburse local governments for all net recycling costs”, and that producer dues fell due in January 202615. The Glass Packaging Institute says Colorado’s glass fees are one-third of Oregon’s.

The plan cycles line up in 2028. Draft OAR 340-090-0720 opens Oregon’s next plan window on 1 January 2028, and SPI’s earlier reporting shows Washington’s and Minnesota’s PRO plans both due on 1 October 2028. For producers, that makes 2028 the year when three state plans are set or reset within ten months, by SPI’s calculation.

Oregon closes comments on operating rules on 30 October, the same day as Washington's cost baseline, while Colorado already reimburses all net costs
StateCurrent stageNext dateCost basisTracker record
PR-US-004CaliforniaCalifornia SB 54 packaging EPR and permanent regulations1 May 2026In force
PR-US-011CaliforniaCalifornia SB 343 recyclability labelling restrictions4 Oct 2026Adopted

Source: DEQ notice, 21 Sep 2026; Washington Ecology; MPCA; CDPHE; SPI Regulation Tracker records PR-US-002, PR-US-003, PR-US-006, PR-US-008, checked 14 Oct 2026.

Stages and cost bases differ, so the states are not directly comparable. USD only; no figures are summed or ranked.

SPI analysis

Producers active in all four states face three comment deadlines within 14 days, from 30 October to 13 November, by SPI’s calculation. Oregon’s is the only one that changes a live fee rate, because the other two set baselines for reimbursement that starts later in the decade.

What it means for you

SPI analysis

These points follow from the sources above and are not legal advice; check with counsel on any filing or classification question.

  • Brand owners: glass users can model 2027 on CAA’s published $0.00 final glass rate, but should keep the $0.04 base rate, and the 2026 rate of $0.10 a pound, in 2028 planning because the drawdowns are a 2027 measure. Check whether any formats fall in the new exemptions before 30 October.
  • Converters: suppliers of raw-meat film, gaylords and reusable crates should map which customer formats leave the fee base, and note that the meat-film exemption ends in 2032.
  • Retailers and grocers: own-label meat and glass-packed lines change cost profile from 2027 if the rules are adopted, and depot-only glass in some wastesheds changes what shoppers can recycle at the kerb.
  • Recyclers and composters: the about 50 composting facilities should budget for data on effectively composted packaging, and remelters of loose shredder metal should check that their intake fits the reprieve to 1 January 2033.
  • Local governments: councils running glass collection lose the incentive and should weigh depot collection from 1 July 2027 against residents’ costs.
  • Large producers: the 25 largest producers by weight should read the proposed life cycle changes in OAR 340-090-0900 to 0930 alongside their first evaluations, which DEQ says fall due at the end of 2026.
  • Finance and investors: ask portfolio companies for Oregon tonnage by material and for their 2027 glass budget assumption.

Track PR-US-002 and the other US records in the SPI Regulation Tracker for the United States, and model exposure in the SPI EPR & Plastic Tax Calculator. For the national picture, read US state packaging EPR.

What to watch next

  • 21 Oct 2026: second public hearing at 6 p.m., by Zoom or phone1.
  • 30 Oct 2026: comments close at 4 p.m.; Washington’s needs-assessment comments close the same day.
  • 13 Nov 2026: Minnesota’s draft 2026 needs assessment comments close, MPCA says.
  • Dec 2026: CAA’s requested approval date for its September plan amendment, and the first life cycle evaluations from large producers are due by 31 December.
  • Jan 2027: DEQ submits the rules to the commission on or after 14 January; the next private recycling claim window opens.
  • 1 Jul 2027: draft glass depot provisions take effect in listed wastesheds.
  • 1 Jan 2028: updated PRO plans begin, running to 31 December 2032.

FAQ

When do comments close on Oregon's rulemaking 3?

DEQ will consider only comments received by 4 p.m. on 30 October 2026. Comments go by email to RMARulemaking3@deq.oregon.gov, by post or as testimony at the hearings on 20 and 21 October.

Will the Oregon glass fee fall in 2027?

DEQ’s notice says the changes could bring a partial reduction in 2027 of the $0.10 a pound fee paid in 2026, with further cuts for 2028. CAA’s board sets the fee. Its 2027 Oregon schedule, published on 1 October 2026, shows a $0.04 a pound base rate for glass and a $0.00 final rate after reserve drawdowns.

Which packaging would become exempt?

The notice lists leased reusable plastic containers, four industrial formats including gaylords of 33.8 ft3 or more, and raw-meat film excluding trays. The raw-meat exemption would expire in 2032.

What happens to residents?

The notice expects about 25 cents a month in costs to shift to residential customers. Some smaller and remote communities may stop on-route glass collection after the local government incentive ends.

When could the rules take effect?

DEQ intends to submit the rules to the commission on or after 14 January 2027, and they take effect only if the commission adopts them. Temporary glass rules adopted in September 2026 already mirror the proposed glass text.

Sources

  1. Oregon Department of Environmental Quality, Recycling Modernization Act Updates 2026, rulemaking page, undated (consulted 2026-10-21)
  2. Oregon Department of Environmental Quality, Notice of Proposed Rulemaking, Recycling Modernization Act Rulemaking 3 (2026), 21 September 2026 (consulted 2026-10-21)
  3. Oregon Department of Environmental Quality, Draft Rules, proposed edits incorporated, undated, linked from the rulemaking page (consulted 2026-10-21)
  4. Oregon Department of Environmental Quality, Draft Rules, edits highlighted, undated, linked from the rulemaking page (consulted 2026-10-21)
  5. Oregon Environmental Quality Commission, 445th regular meeting, 10 and 11 September 2026 (consulted 2026-10-21)
  6. Oregon Department of Environmental Quality, Producers of Covered Products, undated page (consulted 2026-10-21)
  7. Oregon Department of Environmental Quality, Recycling Modernization Act exemptions, undated page (consulted 2026-10-21)
  8. Circular Action Alliance Oregon, Programme plan amendment cover letter to DEQ, 1 September 2026 (consulted 2026-10-21)
  9. Circular Action Alliance Oregon, Oregon Program Plan (2025 to 2027), administrative submission, 1 September 2026 (consulted 2026-10-21)
  10. Circular Action Alliance Oregon, Oregon Program Plan (2025 to 2027), Amended Version, 4 May 2026 (consulted 2026-10-21)
  11. Oregon Department of Environmental Quality, Approval of CAA programme plan amendment on fee ecomodulation, 12 September 2025 (consulted 2026-10-21)
  12. Glass Packaging Institute, The High Cost of the Oregon Outlier, first published February 2026 (consulted 2026-10-21)
  13. Washington Department of Ecology, Needs assessments (Recycling Reform Act), undated page (consulted 2026-10-21)
  14. Minnesota Pollution Control Agency, Packaging Waste and Cost Reduction Act, undated page (consulted 2026-10-21)
  15. Colorado Department of Public Health and Environment, Producer Responsibility Program, undated page (consulted 2026-10-21)

Secondary (context only)

  1. Waste Advantage Magazine, Glass Packaging Institute applauds Oregon DEQ decision to update glass classification, 22 July 2026 (consulted 2026-10-21)

Go deeper

More from SPI News

All articles
  1. Europe · Consumer board and corrugated packaging

    Stora Enso lifted Q3 adjusted EBIT 28% to EUR 161 million on higher board deliveries as its forest demerger advanced

    Stora Enso's adjusted EBIT rose to EUR 161 million from EUR 126 million in the third quarter as containerboard deliveries rose 18%; an extraordinary general meeting on the Bergslagets Skogar demerger is…

    15 min read

  2. Canada · Ontario Blue Box

    Ontario weighs dropping flexible plastic from the Blue Box and would make PROs publish fees; comments close 26 November

    Ontario's ERO notice 026-1058 would give producers itemised PRO invoices and 90 days' notice of mid-year fee rises, and weighs exempting flexible plastic, which Environmental Defence puts at 80,000 tonnes; comments close…

    15 min read

  3. European Union · Heavy metals in packaging

    EU gives lead crystal bottles and flacons a final PPWR exemption. Manufacture ends in 2028, sales in 2029

    The Commission's delegated decision lets lead crystal packaging exceed the PPWR's 100 mg/kg heavy metal cap only until 31 December 2029, with manufacture ending on 31 December 2028; it applies from the…

    15 min read

ClosingAsk the SPI team

Ask the SPI team

What changes for your packaging next quarter?

Tell us your markets and materials. The SPI team walks you through the rules and buyer commitments that affect them.

Prefer email? Write to sales@strategicpackaginginsights.com.

Questions people bring
  1. Q1

    Which packaging rules apply to us in each market we sell in?

    We map each market's EPR, tax, ban, recycled-content, labelling and deposit rules against your materials and formats, and show which are in force, adopted or only proposed.

  2. Q2

    What could EPR fees and plastic taxes cost us next year?

    We apply published fee tables and tax rates to your tonnages and recycled content, and show the result as scenarios with every rate sourced.

  3. Q3

    Can you tell us when a rule changes?

    Yes. The free tracker alerts cover rule changes by country; a monitoring retainer adds monthly notes on what the changes mean for your portfolio.